§ 6.03. Final utility inspection.
Latest version.
A.
Once the public utilities are installed, and prior to the construction of any pavement, the city inspector, the director of public works, the city engineer, and a contractor's representative shall perform a walk-through inspection for all public infrastructure. All testing associated with the utility installation shall be completed prior to the walk-through inspection.
B.
The city engineer shall prepare a list of items that need to be completed prior to the commencement of any paving.